Planning to build or change a dock on Lake McQueeney? You need a Lake McQueeney dock permit from GBRA before work starts. Since Sept. 1, 2026, that means GBRA’s Dock Construction Permit application plus a $600 fee. The same rule covers Lake Dunlap and Lake Placid, per GBRA’s Hydrolakes page.
Who’s in charge?
The Guadalupe-Blanco River Authority (GBRA) owns and runs the lake and its dam. If you own land next to a GBRA hydroelectric lake, you need GBRA approval before you build or modify a dock or other waterfront structure.
GBRA approves the location only. You still need any other permits that apply, such as Guadalupe County’s floodplain permit.
Does my project need a permit?
| Project | GBRA permit? | $600 fee? |
|---|---|---|
| New dock, boathouse, pier, boat slip, retaining wall, ramp or anchored swim platform | Yes | Yes |
| Modification (a change to the location, layout, structure or substructure) | Yes | Yes |
| Adding a structure your permit didn’t include | Yes, a new permit | Yes |
| Building fewer or smaller structures than permitted, no farther from shore | No new permit | No |
| Demolition | Yes | No |
| Routine or preventative maintenance | No, but tell GBRA | No |
Source: GBRA permit form.
Boat lifts on Lake McQueeney sit inside boathouses, so treat a lift as part of the boathouse on your application.
How to apply for a GBRA dock permit
- Get other approvals first. The form lists the City of Seguin, Guadalupe County, the City of New Braunfels, Comal County, Gonzales County, Texas 811 utility locates and the U.S. Army Corps of Engineers. For each, show the approval or mark it “not required.”
- Fill out the form. List the owner, contractor and any agent, plus your property ID or deed number.
- Attach plans. Show the scope of work, measurements and property lines.
- Email it and pay. Send it to dockpermits@gbra.org with the $600 payment. GBRA’s Hydrolakes page has a payment link.
- Wait for approval. No work can start until GBRA issues the permit.
GBRA’s key building rules
GBRA’s form sets a short list of standards:
- Pier length. Piers can’t reach more than 20 feet into the water. GBRA can set a shorter limit.
- Low water. The structure must hold up if the lake drops as much as 12 feet. It should also handle high and fast water.
- Open sides. No dock or structure can be enclosed on the wall sides. Keep that in mind when you plan a Lake McQueeney boathouse.
- Neighbors. Don’t block a neighbor’s land or water access to their structures.
- Lighting. A licensed professional must install any wired lighting.
- Deadline. Finish within 12 months of approval, or the permit is void. GBRA may allow more time for weather or other delays.
Other building specs come from the county, city or state. Where rules differ, the stricter one wins.
Keep it in good shape
You must keep the dock in “good and sound condition.” Loose decking or roofing, broken or missing parts and general disrepair don’t pass. If GBRA notifies you, you have 60 days to fix it or you can lose the permit.
GBRA can also require removal of an unpermitted structure, void a permit or seek a court order.
The county floodplain permit
Guadalupe County requires a Floodplain Development Permit for work in a regulated flood zone, including boat docks and retaining walls. Its application has a shoreline section for docks, boathouses, piers, boat lifts and slips.
The fee is $300, and building without a permit costs double, per the county’s fee schedule. The county inspects before, during and after construction.
Building in, dredging or filling certain waters may also need a Corps of Engineers permit.
Buying a home with a dock
Check the dock before you buy:
- Ask for paperwork. Request the seller’s GBRA permit and any county floodplain permit.
- Look at condition. Compare the dock to GBRA’s “good and sound” standard. A dock inspection can help.
- Check the flood zone. Look up the lot on the county’s floodplain map.
- Know how the permit works. The permit covers construction, not ownership. If a home sells while a dock project is still underway, the permit can transfer to the buyer, and the seller must tell GBRA about the sale. A finished dock doesn’t need a new permit just because the home changes hands.
Our waterfront buyer’s guide covers more, and you can browse Lake McQueeney homes for sale. See also our Lake McQueeney Dam guide and property tax guide.
Get new Lake McQueeney listings first
Want to know the day a waterfront home or lot hits the market? Sign up for free Lake McQueeney listing alerts. You can also browse Lake McQueeney homes for sale and Lake McQueeney lots for sale.
Thinking about selling? Find out what your lake home is worth.
FAQ
Is the GBRA dock permit only for Lake McQueeney?
No. The application and $600 fee also apply on Lake Dunlap and Lake Placid.
Do I need a permit to repair my dock?
Not for routine or preventative maintenance, but you must tell GBRA. Changing the location, layout, structure or substructure is a modification and needs a permit.
Does GBRA approve my dock design?
No. GBRA approves or denies the location only. It doesn’t certify the design or construction.
Do I need a new permit when I buy a home with a dock?
No. The permit is for construction. A finished dock doesn’t need a new permit when the home sells. If the sale happens mid-project, the permit can transfer to the new owner.
Can I start building and apply later?
No. GBRA requires approval before work starts, and the county charges double for floodplain work done without a permit.
The fine print
- Effective date: “Effective September 1, 2026, completion of the Dock Construction Permit application and permit fee (Lake Dunlap, Lake McQueeney, and Lake Placid) is required,” per GBRA’s Hydrolakes page.
- Fee: $600, due with the application. Demolition has no fee. An earlier GBRA form (May 2024) listed the $600 fee and a $100 annual fee as “currently waived.” The current form (Aug. 27, 2026) lists only the $600 fee.
- Structure types on the form: retaining wall, piers, boat slips, dock, boat house, boat launch ramps, jet ski ramp, and anchored swim pads, platforms, water trampolines or inflatables, plus “other.”
- Modification, per GBRA: “any change, addition or alteration in the location, configuration, structure or substructure” of a structure, or one that affects its safety.
- Transfer wording, quoted in full: “this permit may not be assigned or sold but it may be transferred to a subsequent property owner. Owner is responsible for notifying GBRA in the event said property is sold and agrees to notify subsequent owners of the property of the obligation to obtain a new permit.”
- Flood risk: the form says the structure is in a flood-prone area and the owner must follow GBRA and law-enforcement evacuation orders.
- Dredging: no dredging or disposal of fill or spoils except as the law allows. GBRA can void the permit for violations.
- Abandonment: if work isn’t finished in 12 months and you haven’t asked for more time, GBRA can call the project abandoned and require removal at your expense.
- County contact: Guadalupe County Environmental Health, 310 IH 10 W, Seguin. (830) 303-8858, Flood-Permits@guadalupetx.gov. If work goes on during a county stop-work order, the owner and contractor can be ticketed for a Class C misdemeanor, per the county’s permit process.
- GBRA can change its form and rules. Check the current version before you apply. This isn’t legal advice.