If you know Lake McQueeney, you know the dam is the whole story. It’s why the lake went away, why there’s a WCID line on your tax bill, and why the boats and Ski Bees are back. This guide pulls our monthly coverage into one page: how the Lake McQueeney dam was built, why it was replaced, who paid for it, and what it means for owners and buyers. Every date and dollar figure is linked to its source. Where I couldn’t confirm something, I say so.
Lake McQueeney Dam: Quick Facts
| Official name | Lake McQueeney Dam, called “TP-3” by GBRA, per its project sheet |
| Location | Guadalupe River in Guadalupe County, between New Braunfels and Seguin |
| Completed | 1928 |
| Owner and operator | Guadalupe-Blanco River Authority (GBRA), which acquired the dams in 1963, per its Hydrolakes page and the Express-News |
| Who pays for it | Lake McQueeney WCID No. 1 covers the debt service and future operation and maintenance costs, per GBRA’s construction announcement |
| Old gates | Three “bear trap” crest gates |
| New gates | Three hydraulically actuated steel crest gates |
| General contractor | Sundt |
| Construction start | June 19, 2023 |
| Refill began | March 17, 2026, per gvlakes.com |
| Normal pool | 528.83 ft above mean sea level, reached April 21, 2026 |
| 2026 WCID tax rate | $0.3630 per $100 of value, per the WCID’s tax page |
| Flood control? | No. GBRA calls these “pass-through dams that do not control flood waters”, per its 2023 Basin Summary Report |
Timeline: How We Got Here
1928–2015: The original dam
Lake McQueeney Dam was finished in 1928. It is one of six hydroelectric dams built on the Guadalupe in the late 1920s and early 1930s. The state permit covering the system’s dams, No. 1096, is dated June 12, 1929. GBRA says the dam is listed on the National Register of Historic Places.
The dam used three bear-trap-style spillgates. GBRA acquired the system in 1963, from Texas Power Corporation and the Texas Hydro-Electric Corporation, per the San Antonio Express-News. The dams got significant repairs after the floods of 1998 and 2002, but by 2019 GBRA said the dams had passed the end of their useful life at more than 90 years old.
2016–2019: Gates start failing
- 2016: One spillgate at Lake Wood, near Gonzales, failed during a flood, per a Black & Veatch inspection report. GBRA then decided to replace all of the system’s aging gates. In 2018 it began designing hydraulic crest gates for Lake Wood.
- May 14, 2019: Lake Dunlap’s middle spillgate failed at about 7:49 a.m., and Lake Dunlap drained, according to GBRA’s statement. GBRA estimated replacement at roughly $15–35 million per dam, more than its revenues could support.
- Spring–summer 2019 at McQueeney: The lake had already been lowered about 18 inches for gate repairs. After the Dunlap failure, GBRA abandoned those repairs and lowered it about 6 more inches, per the WCID’s election FAQ.
- August 2019: GBRA announced it would drain Lake Gonzales, Meadow Lake, Lake Placid and Lake McQueeney, in that order, starting September 16, 2019. It mailed written notice to affected property owners on August 16, per Seguin Today.
2019–2023: Lawsuits, an injunction and a settlement
Lakefront owners sued. On September 16, 2019, the sides agreed to a 12-month temporary injunction: the four lakes stayed up but were closed to all activity pending trial, per the Texas Tribune.
On July 30, 2020, GBRA settled Skonnord v. GBRA with Lake McQueeney and Lake Placid property owners. GBRA agreed to hold current lake levels until work began on each dam, with financing contracts to follow with new water districts.
A property-owner lawsuit over the spillgate failures was dismissed by a Guadalupe County district court. The Fourth Court of Appeals affirmed in July 2021, and the Texas Supreme Court upheld that ruling in June 2022.
In April 2023, GBRA’s board repealed its interim lake-activity ordinances. The board said a district court had dissolved the temporary injunction and dismissed all claims against GBRA.
Lake Placid had a gate fail to raise after flood operations in October 2021, and Lake Gonzales had a failure in 2021, per the Express-News.
2020–2023: The WCID and the money
The fix was paid for locally, through a special taxing district.
- Creation. Lake McQueeney WCID No. 1 was “created effective April 2020,” according to GBRA’s settlement announcement. Its board first met April 9, 2020.
- October 2020. The district and GBRA signed the financing and operation contract, per GBRA board minutes.
- November 3, 2020. Voters confirmed the district, approved the GBRA contract along with a tax to repay the dam bonds, and approved an operations tax capped at 5 cents per $100, per the WCID’s election FAQ.
- December 2021. GBRA issued $40 million in Contract Revenue Bonds, Series 2021, for the McQueeney dam. The district is obligated to repay them, per its 2022 financial report. GBRA says the funding came through the Texas Water Development Board at below-market interest rates.
- May 6, 2023. Voters approved up to $18 million more in district bonds for the dam and lake work, per the first amendment to the dam contract.
What did it cost? GBRA’s 2024 project sheet estimated $48.7 million. In March 2026, GBRA said each dam cost more than $40 million, and the McQueeney district’s treasurer said it had approved $58 million and spent about $50 million, per the Express-News.
2023–2026: Drawdown and construction
With permits secured, GBRA lowered Meadow Lake first, starting March 27, 2023, and then Lake McQueeney, each over two days, per a Seguin Today drawdown notice. GBRA told its board the drawdown was completed during the week of March 27.
GBRA issued the notice to proceed on June 19, 2023, with an estimated 24-month timeline. The project scope:
- Replace the bear-trap gates with hydraulic steel crest gates
- Modify the spillway structure
- Install new controls and backup power
- Add a dewatering system, so future maintenance can happen with a full lake
- Harden the earthen embankments to meet Texas Commission on Environmental Quality (TCEQ) dam-safety standards
The Lake Dunlap dam was completed in 2023, per the Express-News.
The work ran long. In spring 2023, GBRA had pointed to reopening the lakes “around summer 2025”. GBRA’s Charlie Hickman blamed the delays on three things:
- Differences between the century-old design documents and the actual dams
- Late steel gate manufacturing
- Electrical equipment delays
The WCID’s monthly updates (summarized on this blog) pushed the target from mid-September 2025 into 2026 and reported GBRA enforcing the contract’s late-completion penalties.
2026: The lake comes back
- March 17, 2026: Refilling began, according to GBRA’s lake status page, after final testing passed. At first, Friends of Lake McQueeney said, flows were being shared with Lake Placid downstream, per KSAT.
- April 21, 2026: Lake McQueeney returned to normal pool, 528.83 ft above mean sea level, well ahead of the roughly three months GBRA had projected in March, per the Express-News. GBRA credited recent rainfall.
- Summer 2026: Boats, skiers and the McQueeney Ski Bees were back, including a Fourth of July show at Lake Breeze Ski Lodge.
What the New Dam Means for Homeowners and Buyers
1. The lake is back, but it can still move. GBRA says the lakes are designed to operate near normal pool, though rainfall, streamflow and drought “may influence lake levels over time”. The new gates are run remotely from GBRA’s control room, and stop logs let crews service gates without lowering the lake.
2. It is not a flood-control dam. GBRA describes the Guadalupe Valley dams as “pass-through dams that do not control flood waters”, per its 2023 Basin Summary Report. GBRA’s flood planning document says the hydro lakes “do not contain flood protection benefits”. The WCID’s own FAQ calls McQueeney “a recreational lake only and not a flood control lake”.
GBRA has explained that during floods it lowers the gates as standard protocol, so water passes through at the rate it arrives. That protects the dam and keeps water from flowing over the embankments. (That explanation was given for Lake Placid, a sister dam.) The new armoring reduces the risk of overtopping the dam itself, but that is dam safety, not flood protection for homes. For any property, check the FEMA flood zone, the elevation certificate and flood insurance costs.
3. The WCID tax is part of the cost of owning here. The 2026 district rate is $0.3630 per $100 of value:
| Component | Rate per $100 |
|---|---|
| Debt service | $0.0850 |
| Maintenance | $0.0488 |
| Contract tax (repays the GBRA bonds and covers operations) | $0.2292 |
| Total | $0.3630 |
The rate was $0.2710 in 2022 and 2023, and $0.3551 in 2024 and 2025. That’s $3,630 a year per $1 million of taxable value, before exemptions.
Friends of Lake McQueeney told KSAT the district covers “only owners who have waterfront property”. Confirm any specific property’s status on its tax statement or with the Guadalupe Appraisal District.
4. Hydro revenue helps. GBRA has agreed to pass all gross revenue from selling the dam’s hydroelectric power to the WCID.
5. Docks need GBRA approval. Since September 1, 2026, building or changing a dock on McQueeney requires GBRA’s Dock Construction Permit application and a $600 fee.
6. Respect the dam. GBRA keeps restricted zones 400 feet upstream and downstream of each dam. It also warns about debris and possible bacteria after heavy rain.
For what this means for prices and inventory, see our Lake McQueeney Market Report: September 2026.
Get new Lake McQueeney listings first
Want to know the day a waterfront home or lot hits the market? Sign up for free Lake McQueeney listing alerts. You can also browse Lake McQueeney homes for sale and Lake McQueeney lots for sale.
Thinking about selling? Find out what your lake home is worth.
Lake McQueeney Dam FAQ
Is Lake McQueeney full? GBRA reported normal pool (528.83 ft above mean sea level) as of April 21, 2026. Levels can change; check gvlakes.com for current conditions.
When was the Lake McQueeney dam fixed? Construction started June 19, 2023. Refilling began March 17, 2026, according to GBRA, after final testing passed.
Who owns the Lake McQueeney dam? GBRA owns and operates it. Lake McQueeney WCID No. 1 pays the bond debt and future operating costs.
Why do I pay a WCID tax? District voters chose to fund the new dam themselves. They approved a contract tax to repay the GBRA bonds in 2020 and more bonds in 2023. The 2026 rate is $0.3630 per $100.
Why was Lake McQueeney drained? After gate failures at Lake Wood (2016) and Lake Dunlap (2019), GBRA judged the aging gates unsafe. The 2023 drawdown dried the lakebed for construction.
Does the new dam prevent flooding? No. It’s a pass-through dam, not a flood-control dam.
Can I build or repair a dock now? Yes, with GBRA approval. That means the Dock Construction Permit application plus a $600 fee, effective September 1, 2026. You may also need other local permits.