• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Central Texas Lakes Real Estate home
(830) 556-3505 | Login / Register
  • Search
    • Search All Listings
    • Featured Listings
    • Market Reports
    • New Listing Alerts
  • Lake Lots
  • Lake Houses
  • About
    • About Me
    • Testimonials
  • Contact
  • Home
  • Search
    • Search All Listings
    • Featured Listings
    • Market Reports
    • New Listing Alerts
  • Lake Lots
  • Lake Houses
  • Buyers
    • Buying a Home
    • Why Buy with Me
  • Sellers
    • Selling Your Home
    • Home Valuation
  • Blog
  • About
    • About Me
    • Testimonials
  • Contact

McQueeney dam construction update October 2025

October 16, 2025 by James Walker

As progress continues on the Lake McQueeney Spillgate Replacement and Dam Armoring Project, the Board of Directors for the Lake McQueeney Water Control and Improvement District No. 1 (LMWCID No. 1) offers the latest construction update for October 2025. This update includes new photos, schedule revisions, and a summary of the ongoing and upcoming work at the dam site.


📅 Lake McQueeney Dam Project Timeline Update

Although the project continues to make headway, recent delays involving hydraulic connections and supplier setbacks (notably from Steel-Fab) have pushed the anticipated substantial completion date:

  • Earliest possible completion: January 13, 2026

  • Latest anticipated completion: March 22, 2026

Substantial completion marks the point when all construction is finished, tested, and approved for lake refill. However, the actual refilling date will depend on rainfall and regional drought conditions.


🔧 Construction Milestones for Lake McQueeney Dam

Work Completed on the Lake McQueeney Dam

  • ✅ Bay 3 hydraulic system connection, flushing, and pressure testing

  • ✅ Bay 3 stoplog delivery and dry fit

  • ✅ Maintenance bridge installation

Current Activities at the McQueeney Dam Site

  • ✅ Bay 3 cylinder connections – Started

  • 🏗 Control building modifications and electrical upgrades – Ongoing

  • 🧱 Bay 2 and Bay 3 gate seals – Ongoing

  • 🚧 North & South embankment dam armoring – Ongoing


📸 Construction Progress Photos

Hydraulic gate system and lifting crane at Lake McQueeney Dam

Lake McQueeney Dam gate installation showing construction progress with new hydraulic gates and crane equipment in place.
New spillgate installation progresses at Lake McQueeney Dam as crews move closer to 2026 completion.

Service bridge installation over Lake McQueeney dam

Lake McQueeney Dam service bridge installation with scissor lift and electrical conduit work captured in October 2025.
Scissor lift aids workers installing the Lake McQueeney Dam service bridge while crews complete vital electrical conduit infrastructure below.

Lake McQueeney Dam gate installed with hydraulic arms

Close-up of Lake McQueeney Dam hydraulic hinge system and crane installation during fall 2025 construction phase.
Hydraulic hinge and crane operations highlight ongoing spillgate construction at Lake McQueeney Dam in October 2025.

Electrical conduit installed in Lake McQueeney dam control room

Close-up of electrical conduit installation at Lake McQueeney Dam control room and exterior, October 2025.
Meticulously installed electrical conduit supports automation and control systems for Lake McQueeney Dam, a key step toward 2025 completion.

Interior structure of dam doghouse with lake view

Interior of Lake McQueeney dam doghouse showing electrical conduit work and lake view through service door – Fall 2025.
Inside the dam doghouse at Lake McQueeney, electrical conduit work nears completion as the lake’s return approaches in Winter 2025.

Dam armoring and earthwork underway on the Lake McQueeney embankment

Lake McQueeney dam embankment and foundation under construction with fresh concrete, rock, and erosion control features.
Ongoing concrete and stabilization work along the Lake McQueeney dam embankment ensures structural integrity ahead of lake refill in late 2025.

🔜 Upcoming Construction Tasks

Next Steps in the Spillgate Installation Process

Looking ahead, here are the next planned activities:

  • 🧪 Bay 3 crest gate pretesting

  • 🧱 Final pourbacks on gate seals

  • 🔩 Final bolt torquing and grout installations

  • ⚡ Second round of cathodic protection testing

  • 💧 Stoplog and strut installations for Bay 2

  • 🚧 Embankment concrete and dirt work continues

  • 🔌 Final electrical installations in the control building


⏳ Lake McQueeney Dam Project Timeline Update 

Projected Lake Refill Timeline After Construction

The team continues to work diligently to complete the project safely and efficiently. Despite some delays, the lake remains on track for a refill beginning as early as January 2026—weather permitting (per the McQueeney dam construction update October 2025).

If you live on the lake or own property in the area, remember:
You must clear your lakebed of debris, plants, and structures before the refill.


🌊 Be “Dam Ready” – Winter 2025 Deadline

 

Lake McQueeney “Dam Ready” sign reminding property owners to clear debris before Winter 2025 refill deadline
Lake McQueeney’s “Dam Ready” signs remind property owners to clear debris before the Winter 2025 lake refill deadline.

 


🏡 Planning to Buy or Sell Waterfront Property?

Lake McQueeney is scheduled to return in early 2026, and interest in waterfront homes is already surging.

👉 Visit LakeMcQueeney.com

Filed Under: Uncategorized

Primary Sidebar

Agent Name

Area SpecialistJordan Lippe Walker

(830) 556-3505 Contact Jordan
Listing Alerts Market Reports Your Home's Value

Testimonials

"Jordan worked very hard to find our family the perfect home. She was very professional, always on time and did not try to push properties we were not interested..." view testimonials
- Heather M.
View All

Get In Touch

This field is for validation purposes and should be left unchanged.
Name(Required)
End of Modal

Contact Details

Questions about the market? Wondering what your home is worth? We're here for all your real estate needs, just a message away!

Jordan Lippe Walker
(830) 556-3505
Email

Keller Williams Realty Heritage
8610 FM 725
McQueeney, TX 78123

Get In Touch

This field is for validation purposes and should be left unchanged.
Name(Required)
End of Modal

Contact MeWork With a Local Expert

Whether you are buying or selling, your real estate needs are unique to you. As your local real estate expert I am here to be your guide. Contact me today - I'm here to help.

Contact Me

Footer

Jordan Lippe WalkerTexas Realtor

(830) 556-3505|8610 FM 725, McQueeney, TX 78123 |Contact Jordan
company logo
Equal Housing logo

Download Our IABS Form   •  Consumer Protection Notice
sitemap   •   privacy policy   •   admin   •   ©2026 All Rights Reserved  •  Real Estate Website Design opens in new window by IDXCentral.com

Texas law requires all real estate license holders to give the following information about brokerage services to prospective buyers, tenants, sellers and landlords.