ποΈ Current Construction Highlights
As of mid-May, several key structural elements have been completed or are actively underway:
- β Bay 3 concrete foundation 2nd lift β Completed
- β Bay 3 spillway slab 3.1 lift β Completed
- π Bay 3 spillway slabs 3.2 & 3.3 β In Progress
- π Bay 3 spillway slab 4.1 β Started
- β Bay 2 concrete foundation 1st lift β Completed
- π Bay 2 foundation 2nd lift β In Progress
- π Control building concrete β Started
- β Maintenance bridge bent caps β Completed
- π Maintenance bridge steel spans β Assembly Ongoing
- π Stop log storage foundation β Ongoing
- π North embankment dam armoring β Ongoing
- π South embankment dam armoring β Restarted
π¨ Whatβs Coming Next?
Construction continues to ramp up with new lifts and armoring work scheduled over the coming weeks:
- Bay 3 spillway slab placements 3.2, 3.3, 4.1, and 4.2
- Bay 2 concrete foundation 2nd lift
- Bay 2 spillway slab lift 3
- South abutment concrete lift 1
- Control building modifications and concrete walls
- Ongoing armoring earthwork and concrete on north and south embankments
π Steel Gate Manufacturing Progress
Steel-Fab, Inc. continues fabrication of the new steel gates:
- Manufacturing is actively underway
- Final delivery targeted by end of July 2025
π More Lake McQueeney Resources
To help you stay connected to the lake and community, here are a few helpful links:
- π Lake McQueeney Community Blog β updates on lake life and neighborhood events
- π About Lake McQueeney β explore the lakeβs history, usage, and property info
- π Contact Lake McQueeney Real Estate Team β for property questions, flood zone guidance, or listing inquiries
π¬ Have Questions?
For detailed construction questions, visit the official WCID update here:
π May 2025 Construction Update β LMWCID1
Or use the Contact Us form on their site.
Weβll continue to provide regular updates at LakeMcQueeney.com as this vital infrastructure project nears completion and improves lake safety for generations to come.