Lake McQueeney Dam Update August 2025: Construction Progress, Debris Removal & District Financials
Published: August 2025
Category: Lake McQueeney News, Dam Renovation, Water District Updates
The Lake McQueeney dam update for August brings critical insight into construction progress, lake bed cleanup efforts, and Water Control & Improvement District No. 1โs (WCID No. 1) continued financial strength.
๐ง Spillgate Construction Progress & Timeline
The Lake McQueeney dam update (August 2025) from the Lake McQueeney WCID meeting held August 21, 2025 confirms that the spillgate replacement and dam armoring project remains on track for substantial completion by December 19, 2025 โ despite a 10-day weather delay caused by flooding over July 4th weekend and minor setbacks in steel fabrication.
Key project discussions included:
- Completion of interim transformer solutions to eliminate equipment delays
- Integration of lessons learned from Lake Placid gate issues to improve testing
- Ongoing delivery of four 96-foot-wide gates in bolt-together panels
- Review of expedited delivery and overtime options to stay on schedule

๐ฟ Lake bed Debris Removal Ahead of Refilling
An essential component of the Lake McQueeney construction plan is ensuring a clean and safe lakebed before the refill process begins in late 2025.
- All brush and debris must be fully removed, not just cut
- FOAM committee is coordinating contractor and community cleanup
- Unpermitted barges and stored equipment must be cleared
- A social media campaign is actively reminding residents of their responsibilities
โ WCID No. 1 Audit Results & Financial Health
The August meeting also included a positive financial update, including a clean, unmodified audit opinion for the fiscal year ending April 30, 2025.
Highlights include:
- General fund balance increased by $204,000 to $565,000
- Debt service fund preserved $2.7M after bond and interest payments
- Capital projects fund saw a $4.5M decrease after a $5M GBRA installment
- Total governmental funds balance reached $8.8 million, earning 4%+ average returns
- Property tax collection exceeded 96%, reflecting strong compliance
๐ฐ Monthly Expenses & Community Investment
WCID No. 1 approved $18,588.45 in operational and community expenses for August:
- Legal, audit, bookkeeping, and web expenses: $14,331.45
- Construction crew appreciation event: $4,257
- Catered by Lake Breeze Ski Lodge
- Hosted for 110+ workers on-site
๐ GBRA leaders attended, strengthening resident-contractor relationships.
๐งพ Property Tax Rate Held Flat for 2025
Due to a 6.8% increase in assessed value (to $667 million), the District maintained its total tax rate at 35.551 cents โ the same as last year.
- Growth remained under the 8% state cap, requiring no adjustment
- Projected $323,000 in added revenue with 100% collection rate
- WCID No. 1 retained its “developing” district status for 2025
- This status provides strategic financial flexibility and may be reclassified next year
๐๏ธ Tax Rate Hearing: September 16 at 2:00 PM (quorum required).
๐จ Emergency Management & Flood Safety Enhancements
The District is expanding its flood preparedness strategy:
- 78+ residents responded to a siren effectiveness survey
- Shared with Guadalupe County Emergency Management
- Plans underway for a multi-channel warning system, including:
- Sirens
- Text alerts
- Specific directional messaging for dam-related incidents
- Elevation markers installed in lakeside neighborhoods
๐ฌ Subscribe for alerts or submit questions via the Contact Page.
๐ Hydroelectric Revenue & Bond Repayment Plan
Starting in 2026, WCID No. 1 will apply $430,000 in guaranteed annual hydro revenue toward bond repayments:
- GBRA will ensure full annual amount โ even in partial power years
- Historical net revenue averages over $500,000
- A $900,000 reserve ensures coverage of any shortfalls
- 2027 is expected to be the first normalized hydro year
๐ Action Items for Late Summer
- Confirm board quorum for September 16 tax hearing
- Publish construction photos and updated progress on website
- Distribute audit pages 9โ10 to the public
- Reissue siren survey email to maximize resident input
- Finalize options to avoid steel delivery delays affecting timeline
๐งญ Search-Friendly Terms (SEO Tags):
- Lake McQueeney dam update August
- Spillgate construction McQueeney
- Lake McQueeney WCID tax rate
- Debris removal lake refill timeline
- Lake McQueeney flood safety system